Sequence waves by readiness, logistics, and revenue upside

Bind Smart Meter Readiness scores, warehouse stock, and crew capacity into one executable plan—so political commitments translate into metered, billable endpoints on schedule.

Planning horizon · 12 moReadiness scores

Meters remaining (portfolio)

214,600

Across approved waves; excludes disputed land parcels.

At-risk waves

1

Logistics + readiness conflict — escalate in Action Workflow.

Wave plan & burn-down

Install counts are cumulative within evaluation snapshot.

Wave 4A

Central · Feb 2026Jun 2026

On track
9,820 / 12,400meters79%

Wave 4B

Bushrod · Mar 2026Aug 2026

At risk
4,200 / 8,900meters47%

Wave 5

Paynesville · May 2026Dec 2026

On track
1,100 / 15,200meters7%

Pilot STS

Duala · Jan 2026Apr 2026

On track
2,400 / 2,400meters100%